The sequence
- Position and levels. Where the pool sits relative to the building, the view, the slope and the drainage.
- Excavation. Cutting and shaping, including into sloping ground, with the spoil dealt with properly.
- Base. A compacted, drained base - on fill, this is critical.
- Structure. Reinforced concrete shell and blockwork, designed for water inside and soil pressure outside.
- Pipework and plant. Pump, filtration, pipe routes and plant space, set out before concrete is poured.
- Waterproofing and screed. Before any finish.
- Finishes. Tiling or render, coping and edge details.
- Around the pool. Terraces, steps, showers, and drainage that takes splash-out and rainwater away from the building.
A hillside pool retains ground
On sloping plots the pool often has soil against one side and open air on the other. That makes it a retaining structure with water in it: soil pressure pushing in, water pressure pushing out, and both changing between wet and dry season. Reinforcement, drainage behind the retaining side and a properly compacted base are what stop movement and cracking.
Plant and access to it
The pump and filtration need a sensible location - accessible for service, protected from weather, and not directly under a bedroom window. Deciding this at the drawing stage avoids an unpleasant compromise later.
Water and drainage around the pool
Pool terraces need to fall away from the building, splash-out needs somewhere to go, and in heavy rain the terrace itself becomes a catchment. Pool drainage is part of the property's drainage design, not an afterthought.
Build it with the villa if you can
Excavation, plant routes, retaining and terraces all overlap with the main build. Doing the pool while machinery and teams are already on site is cheaper and produces a better result than returning to a finished property with restricted access. See our swimming pool construction service.